Wellfield Medical Centre, Cheetham Hill

Sector and Service Slideshow

Wellfield Medical Centre, Cheetham Hill

Client: 
Dr Finke
Value: 
£Unknown
Completed: 
2003, 2005, 2006, 2010

Atkinson Peck were appointed over 4 separate phases to extend/refurbish the Medical Centre. Phase 1 included provision of a new first floor common room/staff room facilitated by raising the roof to the front of the Medical Centre. Phase 2 comprised a small extension to the rear of the facility. Phase 3 included the extension of the waiting area to the rear of the Medical centre and the addition of a new Pharmacy, requiring substantial redesign of the existing timber roof structure supported off feature glu-laminated timber purlins. The final phase involved introduction of a new floor above the reception area accessed by a new lift shaft. Throughout all the works the Medical Centre remained in operation, requiring the structural design & programme to be designed accordingly.